Table 1
Dependable Capability Profile
Province of Bohol
As of December 31, 2009
Power Plants |
Installed Capacity (MW) |
Dependable Capability (MW) |
SPC Island Power Corp. (Formerly Bohol Diesel Power Plant) |
22 |
17.5 |
Santa Clara Corp. (Formerly LHEP) |
1.2 |
1.2 |
Janopol Hydroelectric Plant (JHEP) |
5.0 |
5.0 |
BOHECO I – Sevilla Mini-Hydro Corporation (BSMHC) |
2.5 |
2.5 |
TOTALCAPABILITY, Bohol Plants |
30.7 |
26.2 |
Leyte Bohol Interconnection |
80 |
80.0 |
TOTAL |
110.7 |
106.2 |
FORECASTEDDEMAND |
– |
48.0 |
NETRESERVE |
– |
58.2 |
STATUS OF ELECTRIFICATI0N
As of December 2009
Municipality | Potential House | House | % | Member | No.of | Energized | % |
Connection | Connection | Barangay | Barangay | ||||
1. Alburquerque | |||||||
2. Antequera | |||||||
3. Baclayon | |||||||
4. Balilihan | |||||||
5. Batuan | |||||||
6. Bilar | |||||||
7. Calape | |||||||
8. Catigbian | |||||||
9. Carmen | |||||||
10. Clarin | |||||||
11. Corella | |||||||
12. Cortes | |||||||
13. Dauis | |||||||
14. Dimiao | |||||||
15. Inabanga | |||||||
16. Lila | |||||||
17. Loay | |||||||
18. Loboc | |||||||
19. Loon | |||||||
20. Maribojoc | |||||||
21. Panglao | |||||||
22. Sagbayan | |||||||
23. San Isidro | |||||||
24. Sevilla | |||||||
25. Sikatuna | |||||||
26. Tubigon | |||||||
27. Alicia | |||||||
28. Anda | |||||||
29. Bien Unido | |||||||
30. Buenavista | |||||||
31. Candijay | |||||||
32. C.P. Garcia | |||||||
33. Dagohoy | |||||||
34. Danao | |||||||
35. Duero | |||||||
36. Getafe | |||||||
37. Guindulman | |||||||
38. Garcia Hernandez | |||||||
39 Jagna | |||||||
40. Mabini | |||||||
41. Pilar | |||||||
42. San Miguel | |||||||
43. Sierra Bullones | |||||||
44.Talibon | |||||||
45. Trinidad | |||||||
46. Ubay | |||||||
47. Valencia | |||||||
48. Tagbilaran City | |||||||
T O T A L |
Power Plants |
Installed Capacity (MW) |
Dependable Capability (MW) |
SPC Island Power Corp. (Formerly Bohol Diesel Power Plant) |
22 |
17.5 |
Santa Clara Corp. (Formerly LHEP) |
1.2 |
1.2 |
Janopol Hydroelectric Plant (JHEP) |
5.0 |
5.0 |
BOHECO I – Sevilla Mini-Hydro Corporation (BSMHC) |
2.5 |
2.5 |
TOTALCAPABILITY, Bohol Plants |
30.7 |
26.2 |
Leyte Bohol Interconnection |
80 |
80.0 |
TOTAL |
110.7 |
106.2 |
FORECASTEDDEMAND |
– |
48.0 |
NETRESERVE |
– |
58.2 |
span style=”font-size: 10pt; font-family: /strong